dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka | |||||||||
1 | 12/2013 | D1 | 14,9 km | 4 | Hubová, Likavka, Ivachnová | 341 mil. € | 12 491 - 24 900 | 1 | |||||
2 | 3/2020 | R2 | 9,1 km | 4 | Kriváň | 267 mil. € | 8 780 - 11 203 | 3 | |||||
3 | 24. | 12/2025 | R2 | 6,1 km | 4 | Trenčín juh, Trenčianska Turná | 143 mil. € | 12 157 | 3 | ||||
4 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | Kuková | 133 mil. € | 5 814 - 7 518 | 4 | ||||
5 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | Trenčianske Mitice | 277 mil. € | 9 654 - 12 079 | 2 | ||||
6 | 71. - 78. | po 2040 | R7 | 29,2 km | 2 | Bešeňov, Čaka | 230 mil. € | 2 156 - 6 890 | 5 | ||||
7 | 31. | 11/2026 | D3 | 4,0 km | 4 | 179 mil. € | 15 053 | 1 | |||||
8 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 59 mil. € | 12 862 | 3 | |||||
90,0 km |
2 - 4 |
1 628 mil. € |
2 156 - 24 900 | 2,8 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku