dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
||||||||||
1 | 18. | 4/2025 | ![]() | D1 | 1,1 km | 2 | 32 m | 12 mil. € | 2 | 1 | 1/2027 (+5,0) | |||||
2 | 44. - 45. | 2/2029 | ![]() | R2 | 18,0 km | 2 | 1 739 m | Plešivec | 176 mil. € | 5 189 - 6 389 | 5 | 5 | 2/2032 (+4,9) | |||
3 | 44. - 45. | 2/2029 | ![]() | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 2/2033 (+4,5) | ||||||
4 | 46. | 3/2029 | ![]() | D1 | 7,3 km | 4 | 660 m | 321 mil. € | 10 359 | 3 | 3 | 9/2033 (+5,8) | ||||
5 | 47. | 7/2029 | ![]() | R2 | 14,0 km | 2 | 768 m | Turňa nad Bodvou | 117 mil. € | 5 809 - 8 826 | 5 | 4 | 7/2032 (+5,3) | |||
6 | 48. - 49. | 9/2029 | ![]() | R2 | 9,8 km | 2 | 1 074 m | 93 mil. € | 6 452 - 10 032 | 5 | 5 | 9/2032 (+5,6) | ||||
7 | 48. - 49. | 9/2029 | ![]() | R3 | 7,9 km | 2 | 820 m | Mošovce,
Horná Štubňa | 71 mil. € | 5 441 - 8 427 | 4 | 3 | 9/2032 (+4,1) | |||
8 | 53. - 54. | 7/2030 | ![]() | R6 | 11,3 km | 2 | 3 310 m | Mestečko | 222 mil. € | 2 561 - 5 054 | 4 | 3 | 7/2033 (+4,3) | |||
9 | 64. - 68. | 8/2033 | ![]() | D1 | 12,6 km | 4 | 165 m | Dargov | 418 mil. € | 9 503 - 9 802 | 3 | 3 | 8/2036 (+7,9) | |||
9 úsekov |
85,5 km |
2 - 4 |
8 568 m |
1 563 mil. € |
2 561 - 10 359 | 4,0 |
3,6 |
1/2027 - 8/2036 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku