dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
||||||||||
1 | 7/2016 | D4 | 4,4 km | 4 - 6 | 1 | 2 | 11/2021 (+0,4) | |||||||||
2 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | 6,0 | 10/2028 (+4,1) | ||||||
3 | 24. | 12/2025 | R2 | 6,1 km | 4 | 143 mil. € | 12 157 | 9 342 | 3 | 4 | 7,0 | 12/2028 (+4,3) | ||||
4 | 19. | 6/2025 | R4 | 8,2 km | 2 | 94 mil. € | 4 001 | 2 304 | 3 | 3 | 7,0 | 6/2027 (+4,7) | ||||
5 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | 139 mil. € | 4 033 - 8 369 | 3 355 - 7 399 | 4 | 3 | 2,0 | 8/2036 (+7,7) | ||||
6 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 277 mil. € | 9 654 - 12 079 | 7 385 - 9 316 | 2 | 2 | 6,0 | 10/2028 (+3,2) | ||||
7 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 199 mil. € | 5 550 - 9 787 | 4 271 - 7 857 | 2 | 3 | 6,0 | 10/2028 (+4,1) | ||||
8 | 18. | 4/2025 | D1 | 1,1 km | 2 | 12 mil. € | 2 | 1 | 7,0 | 1/2027 (+5,0) | ||||||
9 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 59 mil. € | 12 862 | 10 033 | 3 | 4 | 6,0 | 10/2028 (+4,2) | ||||
9 úsekov |
67,5 km |
2 - 6 |
999 mil. € |
4 001 - 12 862 | 2,4 |
2,7 |
11/2021 - 8/2036 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku