dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 24. | 12/2025 | R2 | 6,1 km | 4 | R2 západ | 143 mil. € | 12 125 | 3 | 4 | ||||
2 | 71. - 78. | po 2040 | R5 | 1,7 km | 2 | D3 Kysuce | 54 mil. € | 12 176 | 3 | 4 | ||||
3 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | R2 západ | 59 mil. € | 13 396 | 3 | 4 | ||||
4 | 19. | 6/2025 | R4 | 8,2 km | 2 | R4 sever | 94 mil. € | 6 944 | 3 | 3 | ||||
5 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | R3 sever (Orava) | 199 mil. € | 6 090 | 2 | 3 | ||||
6 | 7/2019 | R4 | 4,3 km | 4 | R4 stred | 179 mil. € | 15 022 | 1 | 3 | |||||
7 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | R3 sever (Orava) | 77 mil. € | 5 660 | 2 | 2 | ||||
8 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | R2 západ | 277 mil. € | 12 676 - 16 847 | 2 | 2 | ||||
9 | 8/2019 | R2 | 13,5 km | 4 | R2 stred | 142 mil. € | 11 490 | 2 | 2 | |||||
10 | 18. | 4/2025 | D1 | 1,1 km | 2 | D1 sever | 12 mil. € | 4 984 | 2 | 1 | ||||
10 úsekov |
66,8 km |
2 - 4 |
1 235 mil. € |
2,3 |
2,8 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku