dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 1. | 10/2021 | R4 | 14,3 km | 4 | 1 036 m | Košice-juh, Krásna, Hrašovík | 202 mil. € | 9,7 mil. € | 10 088 - 50 895 | 2 | 1 | ||||
2 | 7. | 2/2024 | D1 | 13,5 km | 4 | 1 330 m | Turany 2, Hubová | 1 235 mil. € | 85,6 mil. € | 13 676 - 21 949 | 1 | 1 | ||||
3 | 18. | 4/2025 | D1 | 1,1 km | 2 | 32 m | 12 mil. € | 8,9 mil. € | 2 | 1 | ||||||
4 | 19. | 6/2025 | R4 | 8,2 km | 2 | 453 m | Svidník sever | 94 mil. € | 10,5 mil. € | 4 001 | 3 | 3 | ||||
5 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 1 544 m | Dlhá nad Oravou | 77 mil. € | 13,7 mil. € | 2 | 2 | |||||
6 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 2 764 m | Podbiel | 199 mil. € | 22,0 mil. € | 5 550 - 9 787 | 2 | 3 | ||||
7 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 1 433 m | Trenčianske Mitice | 277 mil. € | 14,7 mil. € | 9 654 - 12 079 | 2 | 2 | ||||
8 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 145 m | 59 mil. € | 18,7 mil. € | 12 862 | 3 | 4 | |||||
9 | 24. | 12/2025 | R2 | 6,1 km | 4 | 1 462 m | Trenčín juh, Trenčianska Turná | 143 mil. € | 16,5 mil. € | 12 157 | 3 | 4 | ||||
10 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | 1 468 m | Lipníky | 105 mil. € | 21,8 mil. € | 14 625 | 2 | 2 | ||||
79,1 km |
2 - 4 |
11 666 m |
2 402 mil. € |
26,7 mil. € |
4 001 - 50 895 | 2,2 |
2,3 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku