dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||
1 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | 6,0 | 10/2028 (+4,1) | |||||
2 | 24. | 12/2025 | R2 | 6,1 km | 4 | 143 mil. € | 12 157 | 3 | 4 | 7,0 | 12/2028 (+4,3) | ||||
3 | 19. | 6/2025 | R4 | 8,2 km | 2 | 94 mil. € | 4 001 | 3 | 3 | 7,0 | 6/2027 (+4,7) | ||||
4 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 277 mil. € | 9 654 - 12 079 | 2 | 2 | 6,0 | 10/2028 (+3,2) | ||||
5 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | 1 020 mil. € | 4 151 - 11 477 | 3 | 5 | 3,0 | 6/2036 (+2,3) | ||||
6 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 199 mil. € | 5 550 - 9 787 | 2 | 3 | 6,0 | 10/2028 (+4,1) | ||||
7 | 18. | 4/2025 | D1 | 1,1 km | 2 | 12 mil. € | 2 | 1 | 7,0 | 1/2027 (+5,0) | |||||
8 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | 92 mil. € | 5 098 - 5 557 | 4 | 2 | 4,0 | po 2040 (0,0) | ||||
9 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 59 mil. € | 12 862 | 3 | 4 | 6,0 | 10/2028 (+4,2) | ||||
10 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | 63 mil. € | 9 492 - 10 279 | 3 | 2 | 3,0 | 11/2030 (+5,2) | ||||
10 úsekov |
117,4 km |
2 - 4 |
2 034 mil. € |
4 001 - 12 862 | 2,7 |
2,8 |
1/2027 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku