dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 24. | 12/2025 | R2 | 6,1 km | 4 | 143 mil. € | 12 157 | 3 | 4 | 12/1998 | 3/2011 | ||||
2 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 59 mil. € | 12 862 | 3 | 4 | 12/1998 | 3/2011 | ||||
3 | 19. | 6/2025 | R4 | 8,2 km | 2 | 94 mil. € | 4 001 | 3 | 3 | 1/2000 | 9/2006 | ||||
4 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 199 mil. € | 5 550 - 9 787 | 2 | 3 | 7/1993 | 12/2009 | ||||
5 | 11. | 6/2024 | R1 | 2,7 km | 4 | 155 mil. € | 16 268 | 4 | 3 | 9/2009 | 2/2020 | ||||
6 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | 7/1993 | 9/2009 | |||||
7 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 277 mil. € | 9 654 - 12 079 | 2 | 2 | 12/1998 | 7/2010 | ||||
8 | 18. | 4/2025 | D1 | 1,1 km | 2 | 12 mil. € | 2 | 1 | 7/2002 | 6/2013 | |||||
50,0 km |
2 - 4 |
1 015 mil. € |
4 001 - 16 268 | 2,6 |
2,8 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku