plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
||||||||||
1 | R2 | 9,1 km | 4 | 2 765 m | 267 mil. € | 8 780 - 11 203 | 3 | 4 | 7,0 | 2024 (+2,8) | ||||
2 | R3 | 4,9 km | 2 | 1 544 m | 77 mil. € | 2 | 2 | 6,0 | 10/2028 (+4,1) | |||||
3 | R2 | 6,1 km | 4 | 1 640 m | 143 mil. € | 12 157 | 3 | 4 | 7,0 | 12/2028 (+4,3) | ||||
4 | R4 | 8,2 km | 2 | 487 m | 94 mil. € | 4 001 | 3 | 3 | 7,0 | 6/2027 (+4,7) | ||||
5 | R2 | 16,0 km | 4 | 1 929 m | 277 mil. € | 9 654 - 12 079 | 2 | 2 | 6,0 | 10/2028 (+3,2) | ||||
6 | R3 | 8,3 km | 2 | 2 956 m | 199 mil. € | 5 550 - 9 787 | 2 | 3 | 6,0 | 10/2028 (+4,1) | ||||
7 | D1 | 1,1 km | 2 | 158 m | 12 mil. € | 2 | 1 | 7,0 | 1/2027 (+5,0) | |||||
8 | R2 | 2,7 km | 4 | 206 m | 59 mil. € | 12 862 | 3 | 4 | 6,0 | 10/2028 (+4,2) | ||||
8 úsekov |
56,4 km |
2 - 4 |
11 685 m |
1 127 mil. € |
4 001 - 12 862 | 2,5 |
2,9 |
7/2024 - 12/2028 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku