dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
odhad INEKO
|
+ posun v rokoch
za posledné cca 4 roky | ||||||||||
1 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | 6,0 | 10/2028 (+4,1) | |||||||
2 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 6 452 - 10 032 | 5 | 5 | 4,0 | 9/2032 (+5,6) | ||||||
3 | 24. | 12/2025 | R2 | 6,1 km | 4 | 143 mil. € | 12 157 | 3 | 4 | 7,0 | 12/2028 (+4,3) | ||||||
4 | 19. | 6/2025 | R4 | 8,2 km | 2 | 94 mil. € | 4 001 | 3 | 3 | 7,0 | 6/2027 (+4,7) | ||||||
5 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 277 mil. € | 9 654 - 12 079 | 2 | 2 | 6,0 | 10/2028 (+3,2) | ||||||
6 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 199 mil. € | 5 550 - 9 787 | 2 | 3 | 6,0 | 10/2028 (+4,1) | ||||||
7 | 18. | 4/2025 | D1 | 1,1 km | 2 | 12 mil. € | 2 | 1 | 7,0 | 1/2027 (+5,0) | |||||||
8 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 59 mil. € | 12 862 | 3 | 4 | 6,0 | 10/2028 (+4,2) | ||||||
8 úsekov |
57,0 km |
2 - 4 |
953 mil. € |
4 001 - 12 862 | 2,8 |
3,0 |
1/2027 - 9/2032 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku