dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 46. | 3/2029 | D1 | 7,3 km | 4 | 321 mil. € | 17 042 | 3 | 3 | 6/2027 | ||||
2 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | NDS údaj neposkytla | 5 | 5 | 6/2028 | ||||
3 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 10 783 | 5 | 5 | 9/2027 | ||||
4 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | 139 mil. € | 6 464 | 4 | 3 | 8/2031 | ||||
5 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 71 mil. € | 12 145 - 15 746 | 4 | 3 | 2/2028 | ||||
6 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | 162 mil. € | 7 061 | 3 | 3 | 8/2031 | ||||
7 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 176 mil. € | 8 348 | 5 | 5 | 1/2027 | ||||
8 | 47. | 7/2029 | R2 | 14,0 km | 2 | 117 mil. € | 15 407 | 5 | 4 | 7/2027 | ||||
8 úsekov |
88,4 km |
2 - 4 |
1 212 mil. € |
4,3 |
3,9 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku