dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 6. | 7/2023 | R2 | 6,8 km | 4 | Ludvíkov Dvor, Haniska | 171 mil. € | 11 764 - 50 895 | 3 | 3 | 7/2026 | |||||
2 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | Plešivec | 176 mil. € | 5 189 - 6 389 | 5 | 5 | 2/2032 | |||||
3 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 2/2033 | |||||||
4 | 46. | 3/2029 | D1 | 7,3 km | 4 | 321 mil. € | 10 359 | 3 | 3 | 9/2033 | ||||||
5 | 47. | 7/2029 | R2 | 14,0 km | 2 | Turňa nad Bodvou | 117 mil. € | 5 809 - 8 826 | 5 | 4 | 7/2032 | |||||
6 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 6 452 - 10 032 | 5 | 5 | 9/2032 | ||||||
7 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | Mošovce,
Horná Štubňa | 71 mil. € | 5 441 - 8 427 | 4 | 3 | 9/2032 | |||||
8 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | Liptovská Osada | 406 mil. € | 7 784 | 4 | 4 | 5/2033 | |||||
8 úsekov |
78,8 km |
2 - 4 |
1 487 mil. € |
5 189 - 50 895 | 4,3 |
4,0 |
7/2026 - 9/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku