dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 277 mil. € | 9 654 - 12 079 | 2 | 2 | 6,0 | 4/2022 | ||||
2 | 26. | 4/2026 | R2 | 20,7 km | 2 | 211 mil. € | 6 969 - 10 726 | 4 | 4 | 5,0 | |||||
3 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 176 mil. € | 5 189 - 6 389 | 5 | 5 | 4,0 | |||||
4 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 4,0 | 11/2024 | |||||
5 | 46. | 3/2029 | D1 | 7,3 km | 4 | 321 mil. € | 10 359 | 3 | 3 | 3,0 | 8/2026 | ||||
6 | 47. | 7/2029 | R2 | 14,0 km | 2 | 117 mil. € | 5 809 - 8 826 | 5 | 4 | 4,0 | |||||
7 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 6 452 - 10 032 | 5 | 5 | 4,0 | |||||
8 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 71 mil. € | 5 441 - 8 427 | 4 | 3 | 4,0 | 7/2020 | ||||
9 | 71. - 78. | po 2040 | R7 | 32,8 km | 2 | 367 mil. € | 2 228 - 6 331 | 5 | 5 | 2,0 | |||||
9 úsekov |
130,0 km |
2 - 4 |
1 766 mil. € |
2 228 - 12 079 | 4,2 |
4,0 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku