dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 3/2020 | ![]() | R2 | 9,1 km | 4 | 267 mil. € | 3 | 4 | 100 % | |||||
2 | 5. | 4/2023 | ![]() | R1 | 8,1 km | 4 | 173 mil. € | - 0,8 % (B. Bystrica - Ružomberok) | 2 | 3 | 7 % | |||
3 | 44. - 45. | 2/2029 | ![]() | R2 | 18,0 km | 2 | 176 mil. € | 5,75 % (Tornaľa - Včeláre) | 5 | 5 | 0 % | |||
4 | 44. - 45. | 2/2029 | ![]() | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 0 % | ||||
5 | 46. | 3/2029 | ![]() | D1 | 7,3 km | 4 | 321 mil. € | 3 | 3 | 0 % | ||||
6 | 47. | 7/2029 | ![]() | R2 | 14,0 km | 2 | 117 mil. € | 5,85 % (Včeláre - Šaca) | 5 | 4 | 0 % | |||
7 | 48. - 49. | 9/2029 | ![]() | R2 | 9,8 km | 2 | 93 mil. € | 5,75 % (Tornaľa - Včeláre) | 5 | 5 | 0 % | |||
8 | 48. - 49. | 9/2029 | ![]() | R3 | 7,9 km | 2 | 71 mil. € | 5,8 % (Martin - Horná Štubňa) | 4 | 3 | 0 % | |||
9 | 59. | 7/2031 | ![]() | R2 | 17,5 km | 4 | 287 mil. € | 2 | 2 | 0 % | ||||
9 úsekov |
95,3 km |
2 - 4 |
1 638 mil. € |
3,8 |
3,8 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku