dátum |
plánovaný
|
odhad NDS
|
<3,5 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 7/2019 | R4 | 4,3 km | 4 | 179 mil. € | 917 - 967 | 1 | 3 | 0,0 | ||||||
2 | 8/2019 | R2 | 13,5 km | 4 | 142 mil. € | 831 - 943 | 2 | 2 | 0,0 | ||||||
3 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | 63 mil. € | 332 - 531 | 3 | 2 | 8,0 | žiadna | ||||
4 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 176 mil. € | 359 - 396 | 5 | 5 | 7,0 | žiadna | ||||
5 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 7,0 | žiadna | |||||
6 | 46. | 3/2029 | D1 | 7,3 km | 4 | 321 mil. € | 974 | 3 | 3 | 7,0 | žiadna | ||||
7 | 47. | 7/2029 | R2 | 14,0 km | 2 | 117 mil. € | 454 - 531 | 5 | 4 | 6,0 | žiadna | ||||
8 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 473 - 644 | 5 | 5 | 7,0 | žiadna | ||||
9 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 71 mil. € | 423 - 703 | 4 | 3 | 7,0 | žiadna | ||||
9 úsekov |
83,3 km |
2 - 4 |
1 295 mil. € |
3,7 |
3,6 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku