dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | ||||||||||
1 | 46. | 3/2029 | D1 | 7,3 km | 4 | 321 mil. € | 10 359 | 3 | 3 | 8/2026 | 9/2033 (+5,8) | |||||
2 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 11/2024 | 2/2033 (+4,5) | ||||||
3 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 6 452 - 10 032 | 5 | 5 | 9/2032 (+5,6) | ||||||
4 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 71 mil. € | 5 441 - 8 427 | 4 | 3 | 7/2020 | 9/2032 (+4,1) | |||||
5 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 176 mil. € | 5 189 - 6 389 | 5 | 5 | 2/2032 (+4,9) | ||||||
6 | 47. | 7/2029 | R2 | 14,0 km | 2 | 117 mil. € | 5 809 - 8 826 | 5 | 4 | 7/2032 (+5,3) | ||||||
7 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | 172 mil. € | 4 | 4 | 4/2029 (+4,1) | |||||||
8 | 59. | 7/2031 | R2 | 17,5 km | 4 | 287 mil. € | 12 819 - 29 988 | 2 | 2 | 9/2024 | 7/2034 (+10,0) | |||||
8 úsekov |
92,3 km |
2 - 4 |
1 370 mil. € |
5 189 - 29 988 | 4,1 |
3,9 |
4/2029 - 7/2034 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku