dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
prebratie
| |||||||||||
1 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 176 mil. € | 5 189 - 6 389 | 49 - 72 | 5 | 5 | 4/2015 | 2/2029 | |||||
2 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 9/2009 | 2/2029 | |||||||
3 | 46. | 3/2029 | D1 | 7,3 km | 4 | 321 mil. € | 10 359 | 51 | 3 | 3 | 3/2029 | ||||||
4 | 47. | 7/2029 | R2 | 14,0 km | 2 | 117 mil. € | 5 809 - 8 826 | 56 - 84 | 5 | 4 | 12/2014 | 7/2029 | |||||
5 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 6 452 - 10 032 | 69 - 107 | 5 | 5 | 4/2015 | 9/2029 | |||||
6 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 71 mil. € | 5 441 - 8 427 | 30 - 78 | 4 | 3 | 2/2016 | 9/2029 | |||||
7 | 59. | 7/2031 | R2 | 17,5 km | 4 | 287 mil. € | 12 819 - 29 988 | 42 - 395 | 2 | 2 | 3/2017 | 7/2031 | |||||
7 úsekov |
78,0 km |
2 - 4 |
1 198 mil. € |
5 189 - 29 988 | 4,1 |
3,9 |
2/2029 - 7/2031 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku