dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
prebratie
|
+ posun v rokoch
za posledné cca 4 roky | ||||||||
16 úsekov |
272,8 km |
2 - 6 |
4 200 mil. € |
3,4 |
3,3 |
9/2028 - 8/2037 |
|||||||||
1 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | R 24,5/120 | 191 mil. € | 4 | 5 | 11/2014 | 9/2028 (+3,5) | ||||
2 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | R 24,5/80, plánované v 1/2-profile | 77 mil. € | 2 | 2 | 2/2016 | 10/2028 (+4,1) | ||||
3 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | R 24,5/100 | 1 020 mil. € | 3 | 5 | 6/2036 (+2,3) | |||||
4 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | R 24,5/120 (100) | 191 mil. € | 3 | 3 | 2/2016 | 6/2034 (+7,0) | ||||
5 | 59. | 7/2031 | R2 | 17,5 km | 4 | R 24,5/100 | 287 mil. € | 2 | 2 | 3/2017 | 7/2034 (+10,0) | ||||
6 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | R 11,5/80 (60) | 94 mil. € | 4 | 2 | 8/2034 (+2,1) | |||||
7 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | R 11,5/80 (60) | 129 mil. € | 3 | 2 | 8/2034 (+2,1) | |||||
8 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | D 33,5/120 | 90 mil. € | 5 | 5 | 3/2016 | 10/2035 (+5,6) | ||||
9 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | D 33,5/120 | 107 mil. € | 5 | 5 | 3/2016 | 10/2035 (+5,9) | ||||
10 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | D 26,5/120
(100) | 418 mil. € | 3 | 3 | 8/2014 | 8/2036 (+7,9) | ||||
11 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | D 26,5/120
(100) | 192 mil. € | 2 | 2 | 8/2014 | 8/2036 (+7,9) | ||||
12 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | D 26,5/120
(100) | 139 mil. € | 4 | 3 | 8/2014 | 8/2036 (+7,7) | ||||
13 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | D 26,5/120
(100) | 162 mil. € | 3 | 3 | 8/2014 | 8/2036 (+7,7) | ||||
14 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | D 26,5/120
(100) | 136 mil. € | 4 | 3 | 8/2014 | 8/2036 (+7,7) | ||||
15 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 305 mil. € | 3 | 3 | 2/2016 | 8/2037 (+5,9) | ||||
16 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 662 mil. € | 4 | 4 | 2/2016 | 8/2037 (+5,9) | ||||
16 úsekov |
272,8 km |
2 - 6 |
4 200 mil. € |
3,4 |
3,3 |
9/2028 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku