dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
prebratie
|
+ posun v rokoch
za posledné cca 4 roky | ||||||||||||
13 úsekov |
203,6 km |
6,7 % |
2 - 6 |
2 913 mil. € |
1 698 - 32 968 | 3,5 |
3,1 |
6/2034 - 8/2037 |
|||||||||||
1 | 57. - 58. | 6/2031 | R3 | 14,0 km | 7,3 % | 4 | R 24,5/120 (100) | 191 mil. € | 14 233 - 18 874 | 2 114 - 2 070 | 3 | 3 | 2/2016 | 6/2034 (+7,0) | |||||
2 | 59. | 7/2031 | R2 | 17,5 km | 20,7 % | 4 | R 24,5/100 | 287 mil. € | 12 819 - 29 988 | 1 901 - 3 009 | 2 | 2 | 3/2017 | 7/2034 (+10,0) | |||||
3 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2,0 % | 2 | R 11,5/80 (60) | 94 mil. € | 7 211 | 919 | 4 | 2 | 8/2034 (+2,1) | ||||||
4 | 60. - 61. | 8/2031 | R3 | 10,9 km | 9,5 % | 2 | R 11,5/80 (60) | 129 mil. € | 5 586 - 10 745 | 791 - 1 514 | 3 | 2 | 8/2034 (+2,1) | ||||||
5 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | D 33,5/120 | 90 mil. € | 32 968 | . . . | 7 510 | 5 | 5 | 3/2016 | 10/2035 (+5,6) | |||||
6 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | D 33,5/120 | 107 mil. € | 5 | 5 | 3/2016 | 10/2035 (+5,9) | ||||||||
7 | 64. - 68. | 8/2033 | D1 | 12,6 km | 1,3 % | 4 | D 26,5/120
(100) | 418 mil. € | 9 503 - 9 802 | 870 - 911 | 3 | 3 | 8/2014 | 8/2036 (+7,9) | |||||
8 | 64. - 68. | 8/2033 | D1 | 18,2 km | 2,3 % | 4 | D 26,5/120
(100) | 192 mil. € | 6 207 - 8 525 | 911 - 840 | 2 | 2 | 8/2014 | 8/2036 (+7,9) | |||||
9 | 64. - 68. | 8/2033 | D1 | 15,8 km | 1,1 % | 4 | D 26,5/120
(100) | 139 mil. € | 4 033 - 8 369 | 461 - 640 | 4 | 3 | 8/2014 | 8/2036 (+7,7) | |||||
10 | 64. - 68. | 8/2033 | D1 | 12,1 km | 3,2 % | 4 | D 26,5/120
(100) | 162 mil. € | 10 444 - 14 783 | 876 - 901 | 3 | 3 | 8/2014 | 8/2036 (+7,7) | |||||
11 | 64. - 68. | 8/2033 | D1 | 15,5 km | 2,2 % | 4 | D 26,5/120
(100) | 136 mil. € | 1 698 - 6 812 | 242 - 519 | 4 | 3 | 8/2014 | 8/2036 (+7,7) | |||||
12 | 69. - 70. | 8/2034 | R3 | 14,0 km | 18,9 % | 2 | R 24,5/120(100), plánované v 1/2-profile | 305 mil. € | 3 | 3 | 2/2016 | 8/2037 (+5,9) | |||||||
13 | 69. - 70. | 8/2034 | R2 | 49,0 km | 5,3 % | 2 | R 24,5/120(100), plánované v 1/2-profile | 662 mil. € | 5 762 - 14 648 | 743 - 1 148 | 4 | 4 | 2/2016 | 8/2037 (+5,9) | |||||
13 úsekov |
203,6 km |
6,7 % |
2 - 6 |
2 913 mil. € |
1 698 - 32 968 | 3,5 |
3,1 |
6/2034 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku