dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||
27 úsekov |
402,1 km |
2 - 6 |
7 299 m |
6 601 mil. € |
1 698 - 93 344 | 2,4 |
2,6 |
12/2019 - 8/2037 | |||||||
1 | 64. - 68. | 8/2033 | ![]() | D1 | 12,6 km | 4 | 53 m | 418 mil. € | 9 503 - 9 802 | 3 | 3 | 8/2036 (+7,9) | |||
2 | 11/2016 | ![]() | D1 | 14,4 km | 4 | 1 660 m | 241 mil. € | 3 166 - 11 562 | 2 | 2 | 12/2019 | ||||
3 | 64. - 68. | 8/2033 | ![]() | D1 | 18,2 km | 4 | 408 m | 192 mil. € | 6 207 - 8 525 | 2 | 2 | 8/2036 (+7,9) | |||
4 | 60. - 61. | 8/2031 | ![]() | R3 | 8,7 km | 2 | 45 m | 94 mil. € | 7 211 | 4 | 2 | 8/2034 (+2,1) | |||
5 | 7/2016 | ![]() | R7 | 17,4 km | 4 | 8 544 - 13 236 | 2 | 3 | 7/2020 (+0,0) | ||||||
6 | 69. - 70. | 8/2034 | ![]() | R3 | 14,0 km | 2 | 60 m | 305 mil. € | 3 | 3 | 8/2037 (+5,9) | ||||
7 | 1/2014 | ![]() | D1 | 11,3 km | 4 | 0 m | 517 mil. € | 23 579 - 28 413 | 2 | 3 | 2021 (+2,1) | ||||
8 | 12/2013 | ![]() | D1 | 14,9 km | 4 | 400 m | 341 mil. € | 12 491 - 24 900 | 1 | 1 | 2023 (+1,0) | ||||
9 | 7/2016 | ![]() | D4 | 4,4 km | 4 - 6 | 1 | 2 | 11/2021 (+0,4) | |||||||
10 | 7/2016 | ![]() | D4 | 22,6 km | 4 - 6 | 32 336 - 93 344 | . . . | 1 | 2 | 11/2021 (+0,4) | |||||
11 | 7/2016 | ![]() | R7 | 8,4 km | 4 | 13 102 - 19 993 | 1 | 1 | 7/2020 (–1,0) | ||||||
12 | 6/2014 | ![]() | D1 | 13,5 km | 4 | 240 m | 555 mil. € | 22 691 - 32 334 | 1 | 2 | 2024 (+4,0) | ||||
13 | 62. - 63. | 10/2032 | ![]() | D2 | 8,5 km | 6 | 90 mil. € | 32 968 | . . . | 5 | 5 | 10/2035 (+5,6) | |||
14 | 57. - 58. | 6/2031 | ![]() | R3 | 14,0 km | 4 | 433 m | 191 mil. € | 14 233 - 18 874 | 3 | 3 | 6/2034 (+7,0) | |||
15 | 64. - 68. | 8/2033 | ![]() | D1 | 15,8 km | 4 | 213 m | 139 mil. € | 4 033 - 8 369 | 4 | 3 | 8/2036 (+7,7) | |||
16 | 57. - 58. | 6/2031 | ![]() | R8 | 54,9 km | 4 | 1 020 mil. € | 4 151 - 11 477 | 3 | 5 | 6/2036 (+2,3) | ||||
17 | 69. - 70. | 8/2034 | ![]() | R2 | 49,0 km | 2 | 295 m | 662 mil. € | 5 762 - 14 648 | 4 | 4 | 8/2037 (+5,9) | |||
18 | 60. - 61. | 8/2031 | ![]() | R3 | 10,9 km | 2 | 164 m | 129 mil. € | 5 586 - 10 745 | 3 | 2 | 8/2034 (+2,1) | |||
19 | 64. - 68. | 8/2033 | ![]() | D1 | 12,1 km | 4 | 154 m | 162 mil. € | 10 444 - 14 783 | 3 | 3 | 8/2036 (+7,7) | |||
20 | 6/2017 | ![]() | D1 | 7,9 km | 4 | 1 513 m | 434 mil. € | 19 072 - 21 988 | 1 | 2 | 7/2021 (0,0) | ||||
21 | 7/2016 | ![]() | R7 | 6,4 km | 4 - 6 | 27 633 - 44 493 | . . . | 1 | 1 | 10/2021 (+0,3) | |||||
22 | 12/2017 | ![]() | D1 | 2,6 km | 4 | 39 mil. € | 14 624 | 1 | 1 | 2021 (+2,2) | |||||
23 | 16. - 17. | 12/2024 | ![]() | R2 | 14,1 km | 2 | 60 m | 272 mil. € | 5 792 - 7 064 | 3 | 2 | 12/2029 (+5,4) | |||
24 | 64. - 68. | 8/2033 | ![]() | D1 | 15,5 km | 4 | 303 m | 136 mil. € | 1 698 - 6 812 | 4 | 3 | 8/2036 (+7,7) | |||
25 | 62. - 63. | 10/2032 | ![]() | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | 10/2035 (+5,9) | |||||
26 | 59. | 7/2031 | ![]() | R2 | 17,5 km | 4 | 228 m | 287 mil. € | 12 819 - 29 988 | 2 | 2 | 7/2034 (+10,0) | |||
27 | 12/2016 | ![]() | D3 | 5,7 km | 4 | 1 071 m | 269 mil. € | 11 465 - 18 743 | 1 | 2 | 2021 (+0,5) | ||||
27 úsekov |
402,1 km |
2 - 6 |
7 299 m |
6 601 mil. € |
1 698 - 93 344 | 2,4 |
2,6 |
12/2019 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku