dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||||
14 úsekov |
200,8 km |
2 - 6 |
2 256 m |
3 077 mil. € |
1 698 - 32 968 | 3,6 |
3,2 |
6/2030 - 8/2036 |
|||||||||
1 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | 101 m | 116 mil. € | 6 651 - 9 113 | 2 | 3 | 6/2030 (+3,7) | ostatné | |||||
2 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 110 m | 71 mil. € | 5 441 - 8 427 | 4 | 3 | 9/2032 (+4,1) | variant TEN-T | |||||
3 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 440 m | 182 mil. € | 7 234 | 4 | 3 | 7/2033 (+4,3) | TEN-T | |||||
4 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 265 m | 222 mil. € | 2 561 - 5 054 | 4 | 3 | 7/2033 (+4,3) | TEN-T | |||||
5 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | 1 020 mil. € | 4 151 - 11 477 | 3 | 5 | 6/2036 (+2,3) | ostatné | ||||||
6 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | 45 m | 94 mil. € | 7 211 | 4 | 2 | 8/2034 (+2,1) | ostatné | |||||
7 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 164 m | 129 mil. € | 5 586 - 10 745 | 3 | 2 | 8/2034 (+2,1) | ostatné | |||||
8 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 32 968 | . . . | 5 | 5 | 10/2035 (+5,6) | ||||||
9 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | 10/2035 (+5,9) | ||||||||
10 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | 53 m | 418 mil. € | 9 503 - 9 802 | 3 | 3 | 8/2036 (+7,9) | TEN-T | |||||
11 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 408 m | 192 mil. € | 6 207 - 8 525 | 2 | 2 | 8/2036 (+7,9) | TEN-T | |||||
12 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | 213 m | 139 mil. € | 4 033 - 8 369 | 4 | 3 | 8/2036 (+7,7) | TEN-T | |||||
13 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | 154 m | 162 mil. € | 10 444 - 14 783 | 3 | 3 | 8/2036 (+7,7) | TEN-T | |||||
14 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | 303 m | 136 mil. € | 1 698 - 6 812 | 4 | 3 | 8/2036 (+7,7) | ostatné | |||||
14 úsekov |
200,8 km |
2 - 6 |
2 256 m |
3 077 mil. € |
1 698 - 32 968 | 3,6 |
3,2 |
6/2030 - 8/2036 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku