dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | ||||||
215,9 km |
2 - 6 |
4 229 mil. € |
3,1 |
3,1 |
11/2021 - 8/2036 |
|||||||
1 | 7/2016 | D4 | 4,4 km | 4 - 6 | 1 | 2 | 11/2021 (+0,4) | |||||
2 | 3/2021 | R3 | 4,4 km | 2 | 70 mil. € | 2 | 2 | 8/2022 (+2,2) | ||||
3 | 1. | 10/2021 | R4 | 14,3 km | 4 | 202 mil. € | 2 | 1 | 10/2024 (+2,6) | |||
4 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | 10/2028 (+4,1) | |||
5 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 199 mil. € | 2 | 3 | 10/2028 (+4,1) | |||
6 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 277 mil. € | 2 | 2 | 10/2028 (+3,2) | |||
7 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 59 mil. € | 3 | 4 | 10/2028 (+4,2) | |||
8 | 24. | 12/2025 | R2 | 6,1 km | 4 | 143 mil. € | 3 | 4 | 12/2028 (+4,3) | |||
9 | 26. | 4/2026 | R2 | 20,7 km | 2 | 211 mil. € | 4 | 4 | 4/2028 (+4,8) | |||
10 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | 125 mil. € | 4 | 4 | 8/2028 (+5,1) | |||
11 | 30. | 10/2026 | R1 | 4,6 km | 4 | 100 mil. € | 4 | 3 | 10/2028 (+3,5) | |||
12 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 6/2033 (+3,3) | |||
13 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 2/2033 (+4,5) | |||
14 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 71 mil. € | 4 | 3 | 9/2032 (+4,1) | |||
15 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | 406 mil. € | 4 | 4 | 5/2033 (+10,2) | |||
16 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 339 mil. € | 4 | 4 | 5/2033 (+10,2) | |||
17 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | 418 mil. € | 3 | 3 | 8/2036 (+7,9) | |||
18 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 192 mil. € | 2 | 2 | 8/2036 (+7,9) | |||
19 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | 139 mil. € | 4 | 3 | 8/2036 (+7,7) | |||
20 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | 162 mil. € | 3 | 3 | 8/2036 (+7,7) | |||
21 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | 136 mil. € | 4 | 3 | 8/2036 (+7,7) | |||
215,9 km |
2 - 6 |
4 229 mil. € |
3,1 |
3,1 |
11/2021 - 8/2036 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku