dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||
1 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | 116 mil. € | 1 396 | 2 | 3 | 9/2026 | 6/2030 (+3,7) | ||||
2 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 71 mil. € | 4 | 3 | 5/2028 | 9/2032 (+4,1) | |||||
3 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | 406 mil. € | 4 | 4 | 2/2030 | 5/2033 (+10,2) | |||||
4 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 339 mil. € | 4 | 4 | 2/2030 | 5/2033 (+10,2) | |||||
5 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | 418 mil. € | 3 434 | 3 | 3 | 11/2031 | 8/2036 (+7,9) | ||||
6 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 192 mil. € | 3 049 | 2 | 2 | 11/2031 | 8/2036 (+7,9) | ||||
7 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | 139 mil. € | 970 | 4 | 3 | 11/2031 | 8/2036 (+7,7) | ||||
8 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | 162 mil. € | 1 766 | 3 | 3 | 11/2031 | 8/2036 (+7,7) | ||||
9 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | 136 mil. € | 923 | 4 | 3 | 11/2031 | 8/2036 (+7,7) | ||||
109,5 km |
2 - 4 |
1 977 mil. € |
3,3 |
3,1 |
6/2030 - 8/2036 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku