dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||||
1 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 820 m | 71 mil. € | 5 441 - 8 427 | 4 | 3 | 4,0 | 1/2029 | |||||
2 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | 907 m | 406 mil. € | 7 784 | 4 | 4 | 3,0 | 9/2030 | |||||
3 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 1 752 m | 339 mil. € | 9 704 - 13 715 | 4 | 4 | 3,0 | 9/2030 | |||||
4 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | 178 m | 94 mil. € | 8,7 km | 7 211 | 4 | 2 | 3,0 | 12/2030 | ||||
5 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | 165 m | 418 mil. € | 12,6 km | 9 503 - 9 802 | 3 | 3 | 2,0 | 8/2032 | ||||
6 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 412 m | 192 mil. € | 18,2 km | 6 207 - 8 525 | 2 | 2 | 2,0 | 8/2032 | ||||
7 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | 180 m | 139 mil. € | 14,7 km | 4 033 - 8 369 | 4 | 3 | 2,0 | 8/2032 | ||||
8 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | 383 m | 162 mil. € | 11,8 km | 10 444 - 14 783 | 3 | 3 | 2,0 | 8/2032 | ||||
9 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | 343 m | 136 mil. € | 15,5 km | 1 698 - 6 812 | 4 | 3 | 2,0 | 8/2032 | ||||
9 úsekov |
111,7 km |
2 - 4 |
5 140 m |
1 956 mil. € |
81,5 km |
1 698 - 14 783 | 3,6 |
3,0 |
1/2029 - 8/2032 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku