dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||
131,6 km |
2 - 4 |
2 213 mil. € |
3,4 |
3,1 |
3/2021 - 8/2033 |
11. - 79. | |||||||
1 | 3/2021 | R3 | 4,4 km | 2 | 70 mil. € | 2 | 2 | 3/2021 | |||||
2 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | 105 mil. € | 2 | 2 | 3/2024 | 74. | |||
3 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 176 mil. € | 5 | 5 | 2/2029 | 79. | |||
4 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 71 mil. € | 4 | 3 | 9/2029 | 11. | |||
5 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | 406 mil. € | 4 | 4 | 5/2031 | 11. | |||
6 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 339 mil. € | 4 | 4 | 5/2031 | 11. | |||
7 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | 418 mil. € | 3 | 3 | 8/2033 | 15. | |||
8 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 192 mil. € | 2 | 2 | 8/2033 | 12. | |||
9 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | 139 mil. € | 4 | 3 | 8/2033 | 13. | |||
10 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | 162 mil. € | 3 | 3 | 8/2033 | 13. | |||
11 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | 136 mil. € | 4 | 3 | 8/2033 | 67. | |||
131,6 km |
2 - 4 |
2 213 mil. € |
3,4 |
3,1 |
3/2021 - 8/2033 |
11. - 79. |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku