plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||||
1 | R4 | 8,0 km | 2 | R 24,5/100, plánované v 1/2-profile | 133 mil. € | 5 814 - 7 518 | 4 | 3 | 6/2025 | 91. | |||||
2 | R8 | 54,9 km | 4 | R 24,5/100 | 1 020 mil. € | 4 151 - 11 477 | 3 | 5 | 6/2027 | 57. | |||||
3 | D1 | 12,6 km | 4 | D 26,5/120
(100) | 418 mil. € | 9 503 - 9 802 | 3 | 3 | 9/2028 | 15. | |||||
4 | D1 | 18,2 km | 4 | D 26,5/120
(100) | 192 mil. € | 6 207 - 8 525 | 2 | 2 | 9/2028 | 12. | |||||
5 | D1 | 15,8 km | 4 | D 26,5/120
(100) | 139 mil. € | 4 033 - 8 369 | 4 | 3 | 9/2028 | 13. | |||||
6 | D1 | 12,1 km | 4 | D 26,5/120
(100) | 162 mil. € | 10 444 - 14 783 | 3 | 3 | 9/2028 | 13. | |||||
7 | D1 | 15,5 km | 4 | D 26,5/120
(100) | 136 mil. € | 1 698 - 6 812 | 4 | 3 | 9/2028 | 67. | |||||
8 | R3 | 14,0 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 305 mil. € | 3 | 3 | 5/2030 | 11. | ||||||
9 | R2 | 49,0 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 662 mil. € | 5 762 - 14 648 | 4 | 4 | 5/2030 | ||||||
200,0 km |
2 - 4 |
3 167 mil. € |
1 698 - 14 783 | 3,3 |
3,2 |
11. - 91. |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku