dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 7/2019 | R4 | 4,3 km | 4 | 179 mil. € | 15 837 - 18 098 | 1 | 3 | 10,0 | 17,5 | 12/2017 | |||||
2 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 199 mil. € | 5 550 - 9 787 | 2 | 3 | 6,0 | 28,0 | 2/2025 | ||||
3 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 71 mil. € | 5 441 - 8 427 | 4 | 3 | 4,0 | 14,3 | 1/2029 | ||||
4 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | 406 mil. € | 7 784 | 4 | 4 | 3,0 | 13,0 | 9/2030 | ||||
5 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 339 mil. € | 9 704 - 13 715 | 4 | 4 | 3,0 | 13,0 | 9/2030 | ||||
6 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | 418 mil. € | 9 503 - 9 802 | 3 | 3 | 2,0 | 25,0 | 8/2032 | ||||
7 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 192 mil. € | 6 207 - 8 525 | 2 | 2 | 2,0 | 24,0 | 8/2032 | ||||
8 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | 162 mil. € | 10 444 - 14 783 | 3 | 3 | 2,0 | 24,0 | 8/2032 | ||||
9 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | 136 mil. € | 1 698 - 6 812 | 4 | 3 | 2,0 | 24,0 | 8/2032 | ||||
99,8 km |
2 - 4 |
2 101 mil. € |
1 698 - 18 098 | 3,0 |
3,1 |
12/2017 - 8/2032 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku