plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
188,5 km |
2 - 6 |
13 038 m |
2 495 mil. € |
2 156 - 32 968 | 4,8 |
4,7 |
2/2028 - po 2040 |
||||||
1 | ![]() | 7,8 km | 2 | 397 m | 73 mil. € | 8 422 | 5 587 | 5 | 4 | 2/2028 | |||
2 | ![]() | 18,0 km | 2 | 1 739 m | 176 mil. € | 8 348 | 5 189 - 6 389 | 5 | 5 | 2/2029 | |||
3 | ![]() | 3,6 km | 4 | 133 mil. € | NDS údaj neposkytla | 5 | 5 | 2/2029 | |||||
4 | ![]() | 14,0 km | 2 | 768 m | 117 mil. € | 15 407 | 5 809 - 8 826 | 5 | 4 | 7/2029 | |||
5 | ![]() | 9,8 km | 2 | 1 074 m | 93 mil. € | 10 783 | 6 452 - 10 032 | 5 | 5 | 9/2029 | |||
6 | ![]() | 8,5 km | 6 | 90 mil. € | 41 057 | 32 968 | . . . | 5 | 5 | 10/2032 | |||
7 | ![]() | 6,9 km | 6 | 107 mil. € | 46 864 | 5 | 5 | 10/2032 | |||||
8 | ![]() | 12,6 km | 4 | 165 m | 418 mil. € | 13 069 | 9 503 - 9 802 | 3 | 3 | 8/2033 | |||
9 | ![]() | 42,1 km | 4 | 631 mil. € | NDS údaj neposkytla | 5 713 - 13 545 | 5 | 5 | |||||
10 | ![]() | 29,2 km | 2 | 3 158 m | 230 mil. € | 2 317 v priemere za dlhý úsek NZ - LC | 2 156 - 6 890 | 5 | 5 | po 2040 | |||
11 | ![]() | 3,1 km | 4 | 60 mil. € | 9 865 | 5 420 - 8 693 | 5 | 5 | |||||
12 | ![]() | 32,8 km | 2 | 5 737 m | 367 mil. € | 2 317 v priemere za dlhý úsek NZ - LC | 2 228 - 6 331 | 5 | 5 | po 2040 | |||
188,5 km |
2 - 6 |
13 038 m |
2 495 mil. € |
2 156 - 32 968 | 4,8 |
4,7 |
2/2028 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku