dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||||
1 | 25. | 1/2026 | D3 | 10,8 km | 4 | 0 m | 309 mil. € | 14 176 - 14 186 | 2 | 4 | 1/2029 (+3,0) | 8. | |||||
2 | 27. | 5/2026 | D3 | 11,2 km | 4 | 0 m | 410 mil. € | 13 886 - 21 743 | 1 | 1 | 5/2029 (+5,1) | 3. | |||||
3 | 31. | 11/2026 | D3 | 4,0 km | 4 | 590 m | 179 mil. € | 15 053 | 1 | 2 | 11/2030 (+6,4) | 4. | |||||
4 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 0 m | 192 mil. € | 6 207 - 8 525 | 2 | 2 | 8/2036 (+7,9) | 12. | |||||
5 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | 3 450 m | 305 mil. € | 3 | 3 | 8/2037 (+5,9) | 11. | ||||||
6 | 71. - 78. | po 2040 | D3 | 3,1 km | 4 | 0 m | 60 mil. € | 5 420 - 8 693 | 5 | 5 | po 2040 (0,0) | ||||||
6 úsekov |
61,3 km |
2 - 4 |
4 040 m |
1 455 mil. € |
5 420 - 21 743 | 2,3 |
2,8 |
1/2029 - po 2040 |
3. - 12. |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku