dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 46. | 3/2029 | D1 | 7,3 km | 9,0 % | 4 | 321 mil. € | 10 359 | 3 | 3 | 3,0 | |||||
2 | 3. | 3/2022 | D1 | 3,5 km | 14,0 % | 8 | 149 mil. € | 62 652 | . . . | 1 | 1 | 8,0 | ||||
3 | 6. | 7/2023 | R2 | 6,8 km | 22,9 % | 4 | 171 mil. € | 11 764 - 50 895 | 3 | 3 | 9,0 | |||||
4 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | 1 020 mil. € | 4 151 - 11 477 | 3 | 5 | 3,0 | ||||||
5 | 4. | 9/2022 | R4 | 10,2 km | 14,0 % | 4 | 299 mil. € | 22 341 - 30 731 | 1 | 3 | 10,0 | |||||
6 | 7. | 2/2024 | D1 | 13,5 km | 9,9 % | 4 | 1 235 mil. € | 13 676 - 21 949 | 1 | 1 | 7,0 | |||||
96,2 km |
13,3 % |
4 - 8 |
3 196 mil. € |
4 151 - 62 652 | 2,0 |
2,7 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku