dátum |
plánovaný
|
odhad NDS
|
<3,5 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 3. | 3/2022 | D1 | 3,5 km | 8 | Ivanka sever | 149 mil. € | 62 652 | . . . | 4 281 | 1 | 1 | |||
2 | 4. | 9/2022 | R4 | 10,2 km | 4 | Kapušany | 299 mil. € | 22 341 - 30 731 | 1 496 - 1 758 | 1 | 3 | ||||
3 | 6. | 7/2023 | R2 | 6,8 km | 4 | Ludvíkov Dvor, Haniska | 171 mil. € | 11 764 - 50 895 | 603 - 2 996 | 3 | 3 | ||||
4 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | Zeleneč nová, Trnava rekonštrukcia | 321 mil. € | 42 774 - 54 519 | . . . | 2 765 - 3 271 | 3 | 2 | |||
5 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | Púchov západ,
Púchov východ,
Dolné Kočkovce | 182 mil. € | 7 234 | 426 | 4 | 3 | ||||
6 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | Záhor | 136 mil. € | 1 698 - 6 812 | 70 - 361 | 4 | 3 | ||||
7 | 71. - 78. | po 2040 | R3 | 58,5 km | 2 | Budča, privádzače D. Niva, Babiná, Hont. Nemce, Dudince, Semerovce | 611 mil. € | 3 247 - 11 434 | 214 - 760 | 4 | 4 | ||||
125,6 km |
2 - 8 |
1 868 mil. € |
1 698 - 62 652 | 2,9 |
2,7 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku