dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||
33 úsekov |
288,2 km |
2 - 8 |
7 305 mil. € |
2,7 |
3,0 |
7/2024 - 6/2033 |
|||||||
1 | 3/2020 | R2 | 9,1 km | 4 | 267 mil. € | 3 | 4 | 2024 (+2,8) | |||||
2 | 3. | 3/2022 | D1 | 3,5 km | 8 | 149 mil. € | 1 | 1 | 9/2025 (+4,6) | ||||
3 | 4. | 9/2022 | R4 | 10,2 km | 4 | 299 mil. € | 1 | 3 | 1/2027 (+4,8) | ||||
4 | 5. | 4/2023 | R1 | 8,1 km | 4 | 173 mil. € | 2 | 3 | 4/2026 (+3,7) | ||||
5 | 6. | 7/2023 | R2 | 6,8 km | 4 | 171 mil. € | 3 | 3 | 7/2026 (+4,3) | ||||
6 | 7. | 2/2024 | D1 | 13,5 km | 4 | 1 235 mil. € | 1 | 1 | 12/2030 (+4,5) | ||||
7 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | 105 mil. € | 2 | 2 | 3/2026 (+4,7) | ||||
8 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | 191 mil. € | 4 | 5 | 9/2028 (+3,5) | ||||
9 | 11. | 6/2024 | R1 | 2,7 km | 4 | 155 mil. € | 4 | 3 | 6/2026 (+3,5) | ||||
10 | 12. | 7/2024 | R3 | 6,5 km | 2 | 70 mil. € | 2 | 2 | 7/2026 (+2,7) | ||||
11 | 13. | 8/2024 | R2 | 8,3 km | 2 | 169 mil. € | 2 | 2 | 8/2026 (+5,1) | ||||
12 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | 227 mil. € | 4 | 4 | 4/2029 (+4,1) | ||||
13 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | 172 mil. € | 4 | 4 | 4/2029 (+4,1) | ||||
14 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | 161 mil. € | 4 | 5 | 5/2029 (+3,5) | ||||
15 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | 272 mil. € | 3 | 2 | 12/2029 (+5,4) | ||||
16 | 18. | 4/2025 | D1 | 1,1 km | 2 | 12 mil. € | 2 | 1 | 1/2027 (+5,0) | ||||
17 | 19. | 6/2025 | R4 | 8,2 km | 2 | 94 mil. € | 3 | 3 | 6/2027 (+4,7) | ||||
18 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | 10/2028 (+4,1) | ||||
19 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 199 mil. € | 2 | 3 | 10/2028 (+4,1) | ||||
20 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 277 mil. € | 2 | 2 | 10/2028 (+3,2) | ||||
21 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 59 mil. € | 3 | 4 | 10/2028 (+4,2) | ||||
22 | 24. | 12/2025 | R2 | 6,1 km | 4 | 143 mil. € | 3 | 4 | 12/2028 (+4,3) | ||||
23 | 25. | 1/2026 | D3 | 10,8 km | 4 | 309 mil. € | 2 | 4 | 1/2029 (+3,0) | ||||
24 | 26. | 4/2026 | R2 | 20,7 km | 2 | 211 mil. € | 4 | 4 | 4/2028 (+4,8) | ||||
25 | 27. | 5/2026 | D3 | 11,2 km | 4 | 410 mil. € | 1 | 1 | 5/2029 (+5,1) | ||||
26 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | 125 mil. € | 4 | 4 | 8/2028 (+5,1) | ||||
27 | 30. | 10/2026 | R1 | 4,6 km | 4 | 100 mil. € | 4 | 3 | 10/2028 (+3,5) | ||||
28 | 31. | 11/2026 | D3 | 4,0 km | 4 | 179 mil. € | 1 | 2 | 11/2030 (+6,4) | ||||
29 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 6/2033 (+3,3) | ||||
30 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | 234 mil. € | 2 | 1 | 6/2030 (+6,9) | ||||
31 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 2/2033 (+4,5) | ||||
32 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 4 | 3 | 5/2033 (+6,1) | ||||
33 | 71. - 78. | po 2040 | R5 | 1,7 km | 2 | 54 mil. € | 3 | 4 | 3/2025 (0,0) | ||||
33 úsekov |
288,2 km |
2 - 8 |
7 305 mil. € |
2,7 |
3,0 |
7/2024 - 6/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku