dátum |
plánovaný
|
odhad NDS
|
>12 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
32 úsekov |
273,6 km |
2 - 8 |
6 489 mil. € |
4 001 - 62 652 | 2,7 |
3,0 |
|||||||||||
1 | 5. | 4/2023 | R1 | 8,1 km | 4 | R 22,5/100 | 173 mil. € | - 0,8 % (B. Bystrica - Ružomberok) | 12 387 - 17 316 | 434 - 541 | 2 | 3 | |||||
2 | 3. | 3/2022 | D1 | 3,5 km | 8 | D 41/120 | 149 mil. € | 62 652 | . . . | 4 737 | 1 | 1 | |||||
3 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | D 41/120 | 234 mil. € | 62 652 | . . . | 4 737 | 2 | 1 | |||||
4 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | D 26,5/100 | 133 mil. € | 5 | 5 | ||||||||
5 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | R 22,5/100, plánované v 1/2-profile | 105 mil. € | 5 304 | 704 | 2 | 2 | ||||||
6 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | R 24,5/80, plánované v 1/2-profile | 77 mil. € | 2 | 2 | ||||||||
7 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | R 11,5/120 | 227 mil. € | 4 | 4 | ||||||||
8 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | R 24,5/120 | 191 mil. € | 6 428 - 9 084 | 565 - 883 | 4 | 5 | ||||||
9 | 6. | 7/2023 | R2 | 6,8 km | 4 | R 24,5/100 | 171 mil. € | 11 764 - 50 895 | 264 - 2 380 | 3 | 3 | ||||||
10 | 3/2020 | R2 | 9,1 km | 4 | DSP spracovaná na R 17,5/100, vyhlásená súťaž na zhotoviteľa stavby na R 24,5/100 | 267 mil. € | 8 780 - 11 203 | 1 143 - 1 188 | 3 | 4 | |||||||
11 | 24. | 12/2025 | R2 | 6,1 km | 4 | R 24,5/120(100) | 143 mil. € | 7,2 % (D1 -Nováky) | 12 157 | 1 263 | 3 | 4 | |||||
12 | 12. | 7/2024 | R3 | 6,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 70 mil. € | -1,3 % (Zvolen-Šahy) | 6 706 - 9 733 | 742 - 818 | 2 | 2 | |||||
13 | 25. | 1/2026 | D3 | 10,8 km | 4 | D 24,5/80 (100) | 309 mil. € | 14 176 - 14 186 | 2 105 - 2 649 | 2 | 4 | ||||||
14 | 19. | 6/2025 | R4 | 8,2 km | 2 | R 24,5/100, plánované v 1/2-profile | 94 mil. € | 5,9 % (Kapušany - V. Komárnik) | 4 001 | 1 361 | 3 | 3 | |||||
15 | 26. | 4/2026 | R2 | 20,7 km | 2 | R 24,5/120, plánované v 1/2-profile | 211 mil. € | 6,4 % (Kriváň - Tornaľa) | 6 969 - 10 726 | 863 - 1 016 | 4 | 4 | |||||
16 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | R 24,5/120 | 161 mil. € | 6 403 - 9 478 | 749 - 874 | 4 | 5 | ||||||
17 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | R 24,5/120(100) | 277 mil. € | 7,2 % (D1 -Nováky) | 9 654 - 12 079 | 1 040 - 1 450 | 2 | 2 | |||||
18 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | R 24,5/80, plánované v 1/2-profile | 199 mil. € | 5 550 - 9 787 | 526 - 829 | 2 | 3 | ||||||
19 | 31. | 11/2026 | D3 | 4,0 km | 4 | D 24,5/80 | 179 mil. € | 15 053 | 2 660 | 1 | 2 | ||||||
20 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | R 22,5/100, plánované v 1/2-profile | 125 mil. € | 6 412 - 8 112 | 655 - 822 | 4 | 4 | ||||||
21 | 4. | 9/2022 | R4 | 10,2 km | 4 | R 24,5/100 | 299 mil. € | 22 341 - 30 731 | 953 - 1 474 | 1 | 3 | ||||||
22 | 10. | 4/2024 | D1 | 3,8 km | 2 | R 11,5/80 | 57 mil. € | 10 312 | 351 | 3 | 5 | ||||||
23 | 18. | 4/2025 | D1 | 1,1 km | 2 | D 11,5/80 | 12 mil. € | 2 | 1 | ||||||||
24 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | R 24,5/120, plánované v 1/2-profile | 272 mil. € | 5 792 - 7 064 | 456 - 489 | 3 | 2 | ||||||
25 | 11. | 6/2024 | R1 | 2,7 km | 4 | R 24,5/80 | 155 mil. € | - 0,8 % (B. Bystrica - Ružomberok) | 16 268 | 1 263 | 4 | 3 | |||||
26 | 30. | 10/2026 | R1 | 4,6 km | 4 | R 24,5/80 | 100 mil. € | - 0,8 % (B. Bystrica - Ružomberok) | 11 611 | 693 | 4 | 3 | |||||
27 | 71. - 78. | po 2040 | R5 | 1,7 km | 2 | R 11,5/70 | 54 mil. € | 7 972 | 2 435 | 3 | 4 | ||||||
28 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | R 24,5/120(100) | 59 mil. € | 7,2 % (D1 -Nováky) | 12 862 | 1 313 | 3 | 4 | |||||
29 | 7. | 2/2024 | D1 | 13,5 km | 4 | D 26,5/100 | 1 235 mil. € | 13 676 - 21 949 | 1 381 - 2 502 | 1 | 1 | ||||||
30 | 13. | 8/2024 | R2 | 8,3 km | 2 | R 22,5/100, plánované v 1/2-profile | 169 mil. € | 5 277 - 6 250 | 692 - 710 | 2 | 2 | ||||||
31 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | R 11,5/120 | 172 mil. € | 4 | 4 | ||||||||
32 | 27. | 5/2026 | D3 | 11,2 km | 4 | D 24,5/80 | 410 mil. € | 13 886 - 21 743 | 2 661 - 2 869 | 1 | 1 | ||||||
32 úsekov |
273,6 km |
2 - 8 |
6 489 mil. € |
4 001 - 62 652 | 2,7 |
3,0 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku