dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||
1 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | 321 mil. € | 42 774 - 54 519 | . . . | 3 | 2 | 11/2008 | 9/2032 (+5,6) | |||
2 | 3. | 3/2022 | D1 | 3,5 km | 8 | 149 mil. € | 62 652 | . . . | 1 | 1 | 11/2008 | 9/2025 (+4,6) | |||
3 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 8/2007 | 6/2033 (+3,3) | |||||
4 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 176 mil. € | 5 189 - 6 389 | 5 | 5 | 7/2010 | 2/2032 (+4,9) | ||||
5 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | 129 mil. € | 2 552 - 2 737 | 4 | 3 | 12/2011 | 11/2031 (+4,8) | ||||
6 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 2 561 - 5 054 | 4 | 3 | 4/2005 | 7/2033 (+4,3) | ||||
6 úsekov |
73,0 km |
2 - 8 |
1 768 mil. € |
2 552 - 62 652 | 3,3 |
3,0 |
9/2025 - 7/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku