dátum |
plánovaný
|
odhad NDS
|
3,5 - 12 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 3. | 3/2022 | D1 | 3,5 km | 8 | D 41/120 | 149 mil. € | 62 652 | . . . | 837 | 1 | 1 | ||||
2 | 7/2016 | R7 | 17,4 km | 4 | R 24,5/120 | 8 544 - 13 236 | 199 - 387 | 2 | 3 | 7/2020 (0,0) | ||||||
3 | 7/2016 | R7 | 8,4 km | 4 | R 31,5/120 | 13 102 - 19 993 | 180 - 274 | 1 | 1 | 7/2020 (0,0) | ||||||
4 | 6. | 7/2023 | R2 | 6,8 km | 4 | R 24,5/100 | 171 mil. € | 11 764 - 50 895 | 236 - 1 254 | 3 | 3 | |||||
5 | 4. | 9/2022 | R4 | 10,2 km | 4 | R 24,5/100 | 299 mil. € | 22 341 - 30 731 | 554 - 748 | 1 | 3 | |||||
6 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | R 24,5/120, plánované v 1/2-profile | 272 mil. € | 5 792 - 7 064 | 192 - 224 | 3 | 2 | |||||
7 | 11. | 6/2024 | R1 | 2,7 km | 4 | R 24,5/80 | 155 mil. € | 16 268 | 400 | 4 | 3 | |||||
8 | 71. - 78. | po 2040 | R7 | 71,3 km | 2 | R 11,5/120 | 553 mil. € | 1 065 - 4 239 | 39 - 162 | 5 | 5 | |||||
8 úsekov |
134,4 km |
2 - 8 |
1 600 mil. € |
1 065 - 62 652 | 2,5 |
2,6 |
7/2020 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku