dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 7/2016 | ![]() | D4 | 22,6 km | 4 - 6 | 32 336 - 93 344 | . . . | 1 | 2 | 11/2000 | ||||
2 | 3. | 3/2022 | ![]() | D1 | 3,5 km | 8 | 149 mil. € | 62 652 | . . . | 1 | 1 | 5/2010 | ||
3 | 39. - 40. | 3/2028 | ![]() | D1 | 19,9 km | 6 | 321 mil. € | 42 774 - 54 519 | . . . | 3 | 2 | 5/2010 | ||
4 | 7/2016 | ![]() | R7 | 6,4 km | 4 - 6 | 27 633 - 44 493 | . . . | 1 | 1 | 11/2013 | 10/2021 | |||
5 | 1. | 10/2021 | ![]() | R4 | 14,3 km | 4 | 202 mil. € | 10 088 - 50 895 | 2 | 1 | 10/2014 | |||
6 | 6/2014 | ![]() | D1 | 13,5 km | 4 | 555 mil. € | 22 691 - 32 334 | 1 | 2 | 3/1997 | ||||
7 | 12/2016 | ![]() | D3 | 5,7 km | 4 | 269 mil. € | 11 465 - 18 743 | 1 | 2 | 11/2000 | 12/2020 (0,0) | |||
8 | 50. - 52. | 5/2030 | ![]() | R4 | 8,0 km | 2 | 133 mil. € | 5 814 - 7 518 | 4 | 3 | 12/2017 | |||
9 | 7/2016 | ![]() | D4 | 4,4 km | 4 - 6 | 1 | 2 | 11/2000 | ||||||
98,3 km |
2 - 8 |
1 629 mil. € |
5 814 - 93 344 | 1,7 |
1,8 |
12/2020 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku