dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 7/2016 | R7 | 17,4 km | 4 | 8 544 - 13 236 | 2 | 3 | 7/2020 (0,0) | ||||||||
2 | 7/2016 | D4 | 22,6 km | 4 - 6 | 32 336 - 93 344 | . . . | 1 | 2 | ||||||||
3 | 7/2016 | R7 | 8,4 km | 4 | 13 102 - 19 993 | 1 | 1 | 7/2020 (0,0) | ||||||||
4 | 3. | 3/2022 | D1 | 3,5 km | 8 | 149 mil. € | 62 652 | . . . | 1 | 1 | 1,0 | |||||
5 | 4. | 9/2022 | R4 | 10,2 km | 4 | 299 mil. € | 22 341 - 30 731 | 1 | 3 | 1,0 | ||||||
6 | 6. | 7/2023 | R2 | 6,8 km | 4 | 171 mil. € | 11 764 - 50 895 | 3 | 3 | 1,0 | ||||||
7 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | 4,0 | |||||||
8 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 191 mil. € | 14 233 - 18 874 | 3 | 3 | 8,0 | 9/2026 | |||||
8 úsekov |
87,8 km |
2 - 8 |
887 mil. € |
8 544 - 93 344 | 1,8 |
2,3 |
7/2020 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku