✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | |||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
# |
dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 7/2016 | R7 | 17,4 km | 4 | 8,6 min. | 17,0 min. | 8 544 - 13 236 | 2 | 3 | 7/2020 (0,0) | ||||||
2 | 7/2016 | R7 | 8,4 km | 4 | 4,2 min. | 10,0 min. | 13 102 - 19 993 | 1 | 1 | 7/2020 (0,0) | ||||||
3 | 3. | 3/2022 | D1 | 3,5 km | 8 | 149 mil. € | 62 652 | . . . | 1 | 1 | ||||||
4 | 4. | 9/2022 | R4 | 10,2 km | 4 | 299 mil. € | 22 341 - 30 731 | 1 | 3 | |||||||
5 | 6. | 7/2023 | R2 | 6,8 km | 4 | 171 mil. € | 11 764 - 50 895 | 3 | 3 | |||||||
6 | 10. | 4/2024 | D1 | 3,8 km | 2 | 57 mil. € | 10 312 | 3 | 5 | |||||||
7 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 77 mil. € | 2,8 min. | 5,5 min. | 2 | 2 | ||||||
8 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 191 mil. € | 14 233 - 18 874 | 3 | 3 | |||||||
8 úsekov |
69,0 km |
2 - 8 |
944 mil. € |
15,7 min. |
32,5 min. |
8 544 - 62 652 | 2,0 |
2,6 |
7/2020 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku