dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
21 úsekov |
192,4 km |
2 - 8 |
4 722 mil. € |
1 698 - 62 652 | 2,5 |
2,9 |
||||||||||
1 | 5. | 4/2023 | R1 | 8,1 km | 4 | R1 BB - RK | R 22,5/100 | 173 mil. € | 12 387 - 17 316 | 2 | 3 | |||||
2 | 3. | 3/2022 | D1 | 3,5 km | 8 | D1 západ | D 41/120 | 149 mil. € | 62 652 | . . . | 1 | 1 | ||||
3 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | R2 stred | R 22,5/100, plánované v 1/2-profile | 105 mil. € | 5 304 | 2 | 2 | |||||
4 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | R7 západ | R 11,5/120 | 227 mil. € | 4 | 4 | ||||||
5 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | R7 západ | R 24,5/120 | 191 mil. € | 6 428 - 9 084 | 4 | 5 | |||||
6 | 1. | 10/2021 | R4 | 14,3 km | 4 | R2 východ, R4 juh | R 24,5/100 | 202 mil. € | 10 088 - 50 895 | 2 | 1 | |||||
7 | 6. | 7/2023 | R2 | 6,8 km | 4 | R2 východ | R 24,5/100 | 171 mil. € | 11 764 - 50 895 | 3 | 3 | |||||
8 | 3/2020 | R2 | 9,1 km | 4 | R2 stred | DSP spracovaná na R 17,5/100, vyhlásená súťaž na zhotoviteľa stavby na R 24,5/100 | 267 mil. € | 8 780 - 11 203 | 3 | 4 | ||||||
9 | 25. | 1/2026 | D3 | 10,8 km | 4 | D3 Kysuce | D 24,5/80 (100) | 309 mil. € | 14 176 - 14 186 | 2 | 4 | |||||
10 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | R7 západ | R 24,5/120 | 161 mil. € | 6 403 - 9 478 | 4 | 5 | |||||
11 | 7/2019 | R4 | 4,3 km | 4 | R4 stred | R 24,5/100 | 179 mil. € | 15 837 - 18 098 | 1 | 3 | ||||||
12 | 10. | 4/2024 | D1 | 3,8 km | 2 | D1 sever | R 11,5/80 | 57 mil. € | 10 312 | 3 | 5 | |||||
13 | 18. | 4/2025 | D1 | 1,1 km | 2 | D1 sever | D 11,5/80 | 12 mil. € | 2 | 1 | ||||||
14 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | R2 východ | R 24,5/120, plánované v 1/2-profile | 272 mil. € | 5 792 - 7 064 | 3 | 2 | |||||
15 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | D1 východ | D 26,5/120
(100) | 136 mil. € | 1 698 - 6 812 | 4 | 3 | |||||
16 | 71. - 78. | po 2040 | R5 | 1,7 km | 2 | D3 Kysuce | R 11,5/70 | 54 mil. € | 7 972 | 3 | 4 | |||||
17 | 7. | 2/2024 | D1 | 13,5 km | 4 | D1 sever | D 26,5/100 | 1 235 mil. € | 13 676 - 21 949 | 1 | 1 | |||||
18 | 3/2021 | R3 | 4,4 km | 2 | R3 sever (Orava) | R 24,5/100 v polovičnom profile | 70 mil. € | 10 334 - 11 542 | 2 | 2 | ||||||
19 | 13. | 8/2024 | R2 | 8,3 km | 2 | R2 stred | R 22,5/100, plánované v 1/2-profile | 169 mil. € | 5 277 - 6 250 | 2 | 2 | |||||
20 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | R7 západ | R 11,5/120 | 172 mil. € | 4 | 4 | ||||||
21 | 27. | 5/2026 | D3 | 11,2 km | 4 | D3 Kysuce | D 24,5/80 | 410 mil. € | 13 886 - 21 743 | 1 | 1 | |||||
21 úsekov |
192,4 km |
2 - 8 |
4 722 mil. € |
1 698 - 62 652 | 2,5 |
2,9 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku