dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||
120,3 km |
2 - 8 |
1 906 mil. € |
2,3 |
2,7 |
||||||||
1 | 7/2016 | ![]() | D4 | 22,6 km | 4 - 6 | 1 | 2 | |||||
2 | 3. | 3/2022 | ![]() | D1 | 3,5 km | 8 | 149 mil. € | 11 991 | 1 | 1 | ||
3 | 6. | 7/2023 | ![]() | R2 | 6,8 km | 4 | 171 mil. € | 1 700 - 4 420 | 3 | 3 | ||
4 | 8. - 9. | 3/2024 | ![]() | R2 | 6,2 km | 2 | 105 mil. € | 2 002 | 2 | 2 | ||
5 | 10. | 4/2024 | ![]() | D1 | 3,8 km | 2 | 57 mil. € | 3 | 5 | |||
6 | 12. | 7/2024 | ![]() | R3 | 6,5 km | 2 | 70 mil. € | 1 489 | 2 | 2 | ||
7 | 13. | 8/2024 | ![]() | R2 | 8,3 km | 2 | 169 mil. € | 2 147 | 2 | 2 | ||
8 | 14. - 15. | 10/2024 | ![]() | R7 | 23,5 km | 2 | 227 mil. € | 1 508 | 4 | 4 | ||
9 | 14. - 15. | 10/2024 | ![]() | R7 | 14,3 km | 2 | 172 mil. € | 965 | 4 | 4 | ||
10 | 18. | 4/2025 | ![]() | D1 | 1,1 km | 2 | 12 mil. € | 908 | 2 | 1 | ||
11 | 25. | 1/2026 | ![]() | D3 | 10,8 km | 4 | 309 mil. € | 2 | 4 | |||
12 | 27. | 5/2026 | ![]() | D3 | 11,2 km | 4 | 410 mil. € | 1 | 1 | |||
13 | 71. - 78. | po 2040 | ![]() | R5 | 1,7 km | 2 | 54 mil. € | 4 932 | 3 | 4 | ||
120,3 km |
2 - 8 |
1 906 mil. € |
2,3 |
2,7 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku