dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 12. | 7/2024 | R3 | 6,5 km | 2 | privádzač Krupina | 70 mil. € | 6 706 - 9 733 | 1 568 - 1 801 | 2 | 2 | |||||
2 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | Zemné | 227 mil. € | 4 | 4 | |||||||
3 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | Mliečany s II/507, Dolný Bar | 161 mil. € | 6 403 - 9 478 | 1 614 - 1 671 | 4 | 5 | |||||
4 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | Podbiel | 199 mil. € | 5 550 - 9 787 | 1 279 - 1 930 | 2 | 3 | |||||
5 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | Moldava nad Bodvou, Šaca | 224 mil. € | 10 140 - 11 010 | 1 815 - 1 961 | 3 | 5 | |||||
6 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | Šahy | 63 mil. € | 9 492 - 10 279 | 1 443 - 1 643 | 3 | 2 | |||||
7 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | Michalovce | 162 mil. € | 10 444 - 14 783 | 1 535 - 1 721 | 3 | 3 | |||||
81,8 km |
2 - 4 |
1 106 mil. € |
5 550 - 14 783 | 3,0 |
3,4 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku