dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
prebratie
|
+ posun v rokoch
za posledné cca 4 roky | ||||||||||
1 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | R 24,5/100, plánované v 1/2-profile | 133 mil. € | 5 814 - 7 518 | 4 | 3 | 12/2014 | 5/2033 (+6,1) | |||||
2 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | R 24,5/100 | 105 mil. € | 14 625 | 2 | 2 | 12/2014 | 8/2029 (+3,8) | |||||
3 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | R 11,5/100 (80) | 182 mil. € | 7 234 | 4 | 3 | 2/2016 | 7/2033 (+4,3) | |||||
4 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | D 26,5/120
(100) | 139 mil. € | 4 033 - 8 369 | 4 | 3 | 8/2014 | 8/2036 (+7,7) | |||||
5 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | R 24,5/100, plánované v 1/2-profile | 124 mil. € | 3 769 - 3 897 | 3 | 3 | 12/2014 | 5/2033 (+6,1) | |||||
6 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | R 24,5/100, plánované v 1/2-profile | 101 mil. € | 3 782 - 6 302 | 4 | 3 | 12/2014 | 5/2033 (+6,1) | |||||
7 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | R 11,5/100 (80) | 222 mil. € | 2 561 - 5 054 | 4 | 3 | 2/2016 | 7/2033 (+4,3) | |||||
7 úsekov |
63,8 km |
2 - 4 |
1 005 mil. € |
2 561 - 14 625 | 3,6 |
2,9 |
8/2029 - 8/2036 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku