dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
||||||||||
1 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 199 mil. € | 6 090 | 5 550 - 9 787 | 2 | 3 | 1/2023 | 10/2028 (+4,1) | ||||
2 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 41 057 | 32 968 | . . . | 5 | 5 | 1/2030 | 10/2035 (+5,6) | |||
3 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | 107 mil. € | 46 864 | 5 | 5 | 1/2030 | 10/2035 (+5,9) | |||||
4 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | 139 mil. € | 6 464 | 4 033 - 8 369 | 4 | 3 | 8/2030 | 8/2036 (+7,7) | ||||
5 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | 662 mil. € | 8 772 - 13 803 | 5 762 - 14 648 | 4 | 4 | 2/2032 | 8/2037 (+5,9) | ||||
5 úsekov |
88,5 km |
2 - 6 |
1 197 mil. € |
4 033 - 32 968 | 4,0 |
4,0 |
10/2028 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku