dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
pôvodný zmluvný termín
| |||||||||||
1 | 7/2016 | D4 | 4,4 km | 4 - 6 | Čierna voda, Rača | 1 | 2 | 3/2020 | |||||||||
2 | 7/2016 | D4 | 22,6 km | 4 - 6 | Jarovce, Rusovce, Ketelec, Rovinka, Ivanka západ, Ivanka sever | 32 336 - 93 344 | . . . | 1 | 2 | 9/2020 | |||||||
3 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | |||||||||
4 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | |||||||||
5 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | Hriadky, Pozdišovce | 192 mil. € | 17,0 min. | 6 207 - 8 525 | 2 | 2 | ||||||
6 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | Sobrance | 139 mil. € | 16,0 min. | 4 033 - 8 369 | 4 | 3 | ||||||
6 úsekov |
77,0 km |
4 - 6 |
1 236 mil. € |
33,0 min. |
4 033 - 93 344 | 2,7 |
3,0 |
3/2020 - 9/2020 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku