dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | ||||||||||
1 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 2/2033 (+4,5) | |||||||
2 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 5 814 - 7 518 | 4 | 3 | 5/2033 (+6,1) | ||||||
3 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 124 mil. € | 3 769 - 3 897 | 3 | 3 | 5/2033 (+6,1) | ||||||
4 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 3 782 - 6 302 | 4 | 3 | 5/2033 (+6,1) | ||||||
5 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 182 mil. € | 7 234 | 4 | 3 | 7/2033 (+4,3) | ||||||
6 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 2 561 - 5 054 | 4 | 3 | 7/2033 (+4,3) | ||||||
7 | 59. | 7/2031 | R2 | 17,5 km | 4 | 287 mil. € | 12 819 - 29 988 | 2 | 2 | 7/2034 (+10,0) | ||||||
8 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | 139 mil. € | 4 033 - 8 369 | 4 | 3 | 8/2036 (+7,7) | ||||||
8 úsekov |
80,9 km |
2 - 4 |
1 321 mil. € |
2 561 - 29 988 | 3,8 |
3,1 |
2/2033 - 8/2036 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku