dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||||
1 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 277 mil. € | 9 654 - 12 079 | 2 | 2 | 5/2024 | 10/2025 | 10/2028 (+3,2) | |||||
2 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | 129 mil. € | 2 552 - 2 737 | 4 | 3 | 11/2026 | 11/2028 | 11/2031 (+4,8) | |||||
3 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 32 968 | . . . | 5 | 5 | 1/2031 | 10/2032 | 10/2035 (+5,6) | ||||
4 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | 1/2031 | 10/2032 | 10/2035 (+5,9) | ||||||
5 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | 136 mil. € | 1 698 - 6 812 | 4 | 3 | 8/2031 | 8/2033 | 8/2036 (+7,7) | |||||
5 úsekov |
54,8 km |
2 - 6 |
738 mil. € |
1 698 - 32 968 | 4,0 |
3,6 |
10/2025 - 8/2033 |
10/2028 - 8/2036 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku