dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||||
1 | 53. - 54. | 7/2030 | ![]() | R6 | 11,2 km | 2 | 440 m | 182 mil. € | 9,2 % (Púchov - hranica SR/ČR) | 7 234 | 4 | 3 | 7/2020 | ||||
2 | 53. - 54. | 7/2030 | ![]() | R6 | 11,3 km | 2 | 265 m | 222 mil. € | 9,2 % (Púchov - hranica SR/ČR) | 2 561 - 5 054 | 4 | 3 | 7/2020 | ||||
3 | 62. - 63. | 10/2032 | ![]() | D2 | 8,5 km | 6 | 90 mil. € | 9,86 % | 32 968 | . . . | 5 | 5 | 7/2020 | ||||
4 | 64. - 68. | 8/2033 | ![]() | D1 | 18,2 km | 4 | 408 m | 192 mil. € | 7,7 % (Bidovce - št. hr. SR/UA) | 6 207 - 8 525 | 2 | 2 | 4/1998 | ||||
5 | 71. - 78. | po 2040 | ![]() | R3 | 58,5 km | 2 | 2 619 m | 611 mil. € | -1,3 % (Zvolen-Šahy) | 3 247 - 11 434 | 4 | 4 | 1/2020 | ||||
5 úsekov |
107,7 km |
2 - 6 |
3 732 m |
1 297 mil. € |
2 561 - 32 968 | 3,8 |
3,4 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku