dátum |
plánovaný
|
odhad NDS
|
>12 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | 227 mil. € | 4 | 4 | |||||||
2 | 25. | 1/2026 | D3 | 10,8 km | 4 | 309 mil. € | 14 176 - 14 186 | 2 105 - 2 649 | 2 | 4 | |||||
3 | 27. | 5/2026 | D3 | 11,2 km | 4 | 410 mil. € | 13 886 - 21 743 | 2 661 - 2 869 | 1 | 1 | |||||
4 | 31. | 11/2026 | D3 | 4,0 km | 4 | 179 mil. € | 15 053 | 2 660 | 1 | 2 | |||||
5 | 47. | 7/2029 | R2 | 14,0 km | 2 | 117 mil. € | 5,85 % (Včeláre - Šaca) | 5 809 - 8 826 | 593 - 844 | 5 | 4 | ||||
6 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 9,86 % | 32 968 | . . . | 5 960 | 5 | 5 | |||
7 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | 107 mil. € | 9,86 % | 5 | 5 | ||||||
8 | 71. - 78. | po 2040 | D3 | 3,1 km | 4 | 60 mil. € | 5 420 - 8 693 | 41 - 376 | 5 | 5 | |||||
82,0 km |
2 - 6 |
1 499 mil. € |
5 420 - 32 968 | 3,5 |
3,8 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku