dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||
1 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 199 mil. € | 5 550 - 9 787 | 2 | 3 | 10/2028 (+4,1) | |||||
2 | 25. | 1/2026 | D3 | 10,8 km | 4 | 309 mil. € | 14 176 - 14 186 | 2 | 4 | 7/2022 | 1/2029 (+3,0) | ||||
3 | 27. | 5/2026 | D3 | 11,2 km | 4 | 410 mil. € | 13 886 - 21 743 | 1 | 1 | 12/2020 | 5/2029 (+5,1) | ||||
4 | 31. | 11/2026 | D3 | 4,0 km | 4 | 179 mil. € | 15 053 | 1 | 2 | 12/2021 | 11/2030 (+6,4) | ||||
5 | 47. | 7/2029 | R2 | 14,0 km | 2 | 117 mil. € | 5 809 - 8 826 | 5 | 4 | 7/2032 (+5,3) | |||||
6 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 32 968 | . . . | 5 | 5 | 10/2035 (+5,6) | ||||
7 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | 10/2035 (+5,9) | ||||||
8 | 71. - 78. | po 2040 | D3 | 3,1 km | 4 | 60 mil. € | 5 420 - 8 693 | 5 | 5 | po 2040 (0,0) | |||||
66,8 km |
2 - 6 |
1 472 mil. € |
5 420 - 32 968 | 3,3 |
3,6 |
10/2028 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku