dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||
319,2 km |
2 - 6 |
3 933 mil. € |
4,3 |
4,3 |
2/2025 - po 2040 |
|||||||
1 | 7/2016 | R7 | 6,4 km | 4 - 6 | 1 | 1 | 10/2021 | |||||
2 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 277 mil. € | 2 | 2 | 2/2025 | |||
3 | 30. | 10/2026 | R1 | 4,6 km | 4 | 100 mil. € | 4 | 3 | 2/2026 | |||
4 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | 73 mil. € | 5 | 4 | 2/2027 | |||
5 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 176 mil. € | 5 | 5 | 2/2028 | |||
6 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 6/2028 | |||
7 | 47. | 7/2029 | R2 | 14,0 km | 2 | 117 mil. € | 5 | 4 | 7/2028 | |||
8 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | 1 020 mil. € | 3 | 5 | 10/2030 | |||
9 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 5 | 5 | 2/2032 | |||
10 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | 2/2032 | |||
11 | 71. - 78. | po 2040 | R1 | 42,1 km | 4 | 631 mil. € | 5 | 5 | ||||
12 | 71. - 78. | po 2040 | R7 | 29,2 km | 2 | 230 mil. € | 5 | 5 | po 2040 | |||
13 | 71. - 78. | po 2040 | D3 | 3,1 km | 4 | 60 mil. € | 5 | 5 | ||||
14 | 71. - 78. | po 2040 | R7 | 32,8 km | 2 | 367 mil. € | 5 | 5 | po 2040 | |||
15 | 71. - 78. | po 2040 | R7 | 71,3 km | 2 | 553 mil. € | 5 | 5 | po 2040 | |||
319,2 km |
2 - 6 |
3 933 mil. € |
4,3 |
4,3 |
2/2025 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku