dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
prebratie
| |||||||||
273,8 km |
2 - 6 |
2 949 mil. € |
1 065 - 32 968 | 4,8 |
4,6 |
33 - 78 |
|||||||||
1 | 71. - 78. | po 2040 | 32,8 km | 2 | 367 mil. € | 2 228 - 6 331 | 5 | 5 | 9,0 | 5/2016 | 78 | ||||
2 | 71. - 78. | po 2040 | 71,3 km | 2 | 553 mil. € | 1 065 - 4 239 | 5 | 5 | 9,0 | 5/2016 | 77 | ||||
3 | 71. - 78. | po 2040 | 29,2 km | 2 | 230 mil. € | 2 156 - 6 890 | 5 | 5 | 7,0 | 5/2016 | 76 | ||||
4 | 71. - 78. | po 2040 | 3,1 km | 4 | 60 mil. € | 5 420 - 8 693 | 5 | 5 | 5,0 | 6/2014 | 75 | ||||
5 | 71. - 78. | po 2040 | 42,1 km | 4 | 631 mil. € | 5 713 - 13 545 | 5 | 5 | 10,0 | 74 | |||||
6 | 62. - 63. | 10/2032 | 8,5 km | 6 | 90 mil. € | 32 968 | . . . | 5 | 5 | 9,0 | 3/2016 | 62 | |||
7 | 62. - 63. | 10/2032 | 6,9 km | 6 | 107 mil. € | 5 | 5 | 9,0 | 3/2016 | 61 | |||||
8 | 60. - 61. | 8/2031 | 8,7 km | 2 | 94 mil. € | 7 211 | 4 | 2 | 9,0 | 59 | |||||
9 | 48. - 49. | 9/2029 | 9,8 km | 2 | 93 mil. € | 6 452 - 10 032 | 5 | 5 | 7,0 | 4/2015 | 48 | ||||
10 | 47. | 7/2029 | 14,0 km | 2 | 117 mil. € | 5 809 - 8 826 | 5 | 4 | 6,0 | 12/2014 | 47 | ||||
11 | 44. - 45. | 2/2029 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 7,0 | 9/2009 | 45 | |||||
12 | 44. - 45. | 2/2029 | 18,0 km | 2 | 176 mil. € | 5 189 - 6 389 | 5 | 5 | 7,0 | 4/2015 | 44 | ||||
13 | 37. - 38. | 2/2028 | 7,8 km | 2 | 73 mil. € | 5 587 | 5 | 4 | 6,0 | 4/2015 | 38 | ||||
14 | 32. - 33. | 12/2026 | 18,0 km | 2 | 224 mil. € | 10 140 - 11 010 | 3 | 5 | 5,0 | 12/2014 | 33 | ||||
273,8 km |
2 - 6 |
2 949 mil. € |
1 065 - 32 968 | 4,8 |
4,6 |
33 - 78 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku